The production cycle of SMT surface mount PCBA is not fixed and is influenced by various factors, ranging from a few days to several weeks. A typical
small to medium-sized batch order cycle may be as follows:
Engineering review and material preparation: 1-3 days (document confirmation, component procurement - these are the most influential stages).
SMT production: 1-3 days (including steel mesh production, solder paste printing, SMT, reflow soldering, online testing).
Post processing (if any): 0.5-2 days (insertion, wave soldering/selective soldering, cleaning).
PCBA testing: 1-3 days (testing plan development, fixture production, actual testing).
Packaging and transportation: 0.5 days.
Therefore, a smooth order, from the complete set of materials to the shipment of finished products, usually requires 3-7 working days for the core production testing process. Combining preliminary engineering and logistics, the total delivery time may be around 1-2 weeks. Sampling is usually faster (3-7 days), while mass production depends on the specific quantity.